Upper Kolab
H.E Project
Commissioning Date
STAGE-1 ( 3 UNITS)
- Approval by planning commission: Auguest 1975
- Comencement of work : 1976
- Completion of work : 1990
STAGE-2 ( 4TH UNIT)
- Approval by planning commission: 1987
- Completion of work : 1995
Date of Commissioning
- Unit 1 :15.03.1988
- Unit 2 : 14.04.1988
- Unit 3 : 10.02.1990
- Unit 4 : 12.01.1993