
The important event of commissioning of 1st Stage and 2nd stage works are given below.
| UNIT-I | UNIT-II | UNIT-III | UNIT-IV | |
|---|---|---|---|---|
| FIRST SPINNING SYNCHRONISED TO GRID | 19.12.87 | 29.03.88 | 24.01.90 | 03.07.92 |
| COMMERCIAL | 15.03.88 | 14.04.88 | 10.02.90 | 22.07.92 |
| OPERATION | 15.03.88 | 16.04.88 | 10.02.90 | 12.01.93 |