Unit avaliability in % from 1996-97 to 2006-07
Year |
Unit-I |
Unit-II |
Unit-III |
Unit-IV |
Unit-V |
|
2006-07
|
77.61 |
80.66 | -------- | 99.40 | 95.64 | |
2005-06
|
94.55 |
92.24 | 64.22 | 55.19 | 99.60 | |
2004-05
|
85.03 |
88.63 | 82.71 | 94.28 | 93.19 | |
2003-04 |
89.51 | 78.44 | 99.24 | 89.58 | 91.61 | |
2002-03 |
39.22 |
71.77 |
96.31 |
86.27 |
89.47 | |
2001-02 |
69.00 |
81.63 |
81.68 |
58.12 |
90.66 |
|
2000-01 |
95.77 |
76.87 | 92.3 |
65.35 |
74.07 |
|
1999-2000 |
77.37 |
60.50 |
71.62 | 82.97 |
59.70 |
|
1998-99 |
89.99 |
81.96 |
85.08 | 74.57 |
84.55 |
|
1997-98 |
47.13
|
94.43 |
91.17 |
81.63 |
87.04 | |
1996-97 |
------ |
82.87 |
89.95 |
92.00 |
95.13 |
|