Copyright © 2003 Orissa Hydro power Corporation Ltd. All Rights Reserved.
Best view (800x600) Internet explore 4.0 and above.

Important Events

Welcome
Project Features
Important Events
Commissioning
dates
Salient Features
Generation

Power plant economics

Staff strength
Unit Availablity
Reach at Us


 

Power Generation from the Station has been taken up in two Stages:- Stage-I having two units and Stage-II having three Units.

    STAGE-I WORKS

    The Stage-I of the Hydro Electric Power Station has two generating Units of 50 M.W. each with a firm power of 60 MW (corresponding to a firm generation of 526 MU per year).

    The Stage-I work also includes installation of penstock Gates, Penstock, Draft Tube Gates etc. for three more Units, covered under Stage-II work. The power house Auxiliaries, such as, two numbers of Electrical Overhead Travelling Cranes, Gantry Cranes for hosting the Draft Tube Gates / Penstock Gates / Stoplogs, Ventilation and Air Conditioning Systems, Passenger Lifts, Station Dewatering and Drainage System, Station Compressor System, Station D.C. System, Station Auxiliary Power Supply System etc. are also covered under Stage-I.

    For the evacuation of power from the Station a 220 KV Switchyard, having 8 bays, i.e. 2 for the Generating Units, 1 for Station Transformer, 1 for bus coupler, 4 for outgoing feeders (two to Rengali switchyard, one to kaniha Super Thermal Station and one to NALCO), has been provided under Stage-I.

    A House Service Set of capacity 500 KW with a Francis turbine has been installed under Stage-I to provide start-up power in case of total power failure.

    46% of the cost of the Dam has been apportioned to Power Generation. The Power Scheme estimated cost for Stage-I is as below :

    Sl.No.

     

    Initial Rs. in Lakhs

    Last Revised Rs. in lakhs

    1.

    Cost of the Dam apportioned to Power Generation (46%)

    1932.00

    7813.56

    2.

    Power House Civil works

    330.00

    2635.00

    3.

    Electrical works

    1270.68

    3588.00

       

    3532.68

    14036.56

    The expenditure of Electrical works is Rs.3566.82 Lakhs upto 31.3.92

    Units-I & II have been commissioned and synchronised to Orissa Grid on 27.8.85 & 26.3.86 respectively. They are now in commercial operation.

    STAGE-II WORKS

The Stage-II of the Power Station has three more generating Units (Unit Nos.III, IV & V) each of 50 MW capacity. The secondary generation would be 225 MU (equivalent to annual average power of 25.68 MW).The administrative approval for stage-II works was communicated by I&P Department, Govt. of Orissa on their letter no 26567 & 33407 dated 13.06.96.

For transmission of power of Stage-II Units three more bays have been provided in the existing 220 KV switchyard.

The power scheme estimated cost for stage-II is as below:-

Sl.No.

 

Initial Rs. in Lakhs

Last Revised Rs. in lakhs

1.

Power House Civil works

258.00

1122.00

2.

Electrical works

3979.00

6274.00

The erection works of stage-II units started during the year 1987, Unit-III, Unit-IV & Unit-V have been commissioned and synchronised to Orissa Grid on 10.8.89, 19.3.90 and 14.8.92 respectively.

The total expenditure on dam Rs.171,01,27,460/- up to March 1993 and power house works.