Welcome To Machkund HE Project


 

Machhkund Hydro Electric Scheme was conceived during early 1940's a joint Hydel Project between erstwhile composite State of Madras and State of Orissa on the river Machhkund. It is the first major Hydro electric Project located in the state of Orissa, executed through an inter-state agreement between Orissa and the then Madras Government on 04.01.1945. It was taken up as a joint project between the two states.

As per the terms of the agreement :-

 

IMPORTANT EVENTS

YEAR

EVENTS

May 1929

Preliminary reconnaissance of Machhkund catchment and falls

1940

Detailed reconnaissance

July 1943

Survey & field work completed

1946

Project work started

4th Jan,1947

Joint Board of Control constituted by Govt of Madras

24th Feb,1950

First meeting of Joint Board of Control held at Machhkund

9th Aug,1954

Reconstitution of Joint Board of Control by Govt. of Andhra