The project
was administratively approved for Rs. 16,63,43,529/- and subsequently revised
to
Rs. 18,27,91,514/-. The detail break up and phasing of expenditure is given
bellow.
|
Main A/c |
Name of work |
Amount |
Revised |
|
|
No |
|
|
Amount |
|
|
|
|
|
|
|
|
1 |
Preliminary Investigation, |
1,60,000 |
1,60,000 |
|
|
|
|
|
|
|
|
2 |
||||
|
3 |
Jalaput Dam |
|||
|
4 |
Diversion Dam |
125,40,000 |
||
|
5 |
|
80,27,000 |
||
|
|
|
tunnel |
|
|
|
6 |
MA130 |
Tunnel pond dam |
18,00,000 |
|
|
7 |
MA140A |
Tunnel head works
pipe |
67,72,100 |
|
|
|
|
|
|
|
|
8 |
MA140B |
Penstock haulage
track etc |
129,43,750 |
|
|
9 |
MA 150 |
Power station
building |
||
|
10 |
MA 160 |
Generating plant |
232,10,050 |
191,55,550 |
|
11 |
MA 170 |
Power station
auxiliary |
16,23,000 |
|
|
12 |
MA 180 |
8,01,000 |
||
|
13 |
MA 190 |
Transformer yard |
81,57,000 |
|
|
14 |
MA 200 |
72,70,661 |
88,72,861 |
|
|
15 |
MA 210 |
Local service
line for |
6,94,000 |
|
|
|
|
Power & Light |
|
|
|
16 |
MA 220 |
Permanent building |
||
|
17 |
MA 230 |
Water supply,
sewerage fire |
13,08,720 |
11,88,185 |
|
|
|
protection etc. |
|
|
|
18 |
MA 240 |
1,56,200 |
||
|
19 |
MA 040 |
93,12,371 |
||
|
20 |
MA 010, |
169,08,856 |
||
|
|
general charges |
|
|
|
|
21 |
MA 030B |
Engineering Construction |
46,84,502 |
1401,00,000 |
|
|
|
equipment |
|
|
|
|
|
Total |
||
|
|
|
|
(-) 85,10,000 |
|
|
|
|
G. Total |
l6,63,43,529 |
18,27,91,514 |
| PHASING OF EXPENDITURE | ||||
| YEAR | EXPENDITURE(Rs. Lakh) | |||
| 1948 - 1955 | 869.33 | |||
| 1955-56 | 161,38 | |||
| 1956-57 | 243,08 | |||
| 1957-58 | 198,32 | |||
| 1958-59 | 109.23 | |||
| 1959-60 | 33,11 | |||
| 1960-61 | 28.52 | |||
| 1961-62 | 36,45 | |||
| 1962-63 | 24.73 | |||
| 1963-64 | 27.46 | |||
| 1964-65 | 22,74 | |||
| 1965-66 | 73.56 | |||