| The Concreting of Power Plant was commenced during | May 1969 |
| Power House Concreting | November 19,1969 |
| The First turbine spiral casing installation was started during | August 1971 |
| Installation of the Generator was commenced during | May 1972 |
| Reservoir filling | August 15, 1972 |
| Water was admitted into the Balimela power tunnel | May 23, 1973. |
| The first turbine was put on trial run | At the end of May 1973. |
| First unit was commissioned | August 14, 1973. |